SAP Activate Quiz — Implementation Tools, Methodology, Agile Project Delivery
1. What are the 3 key pillars of the SAP Activate Implementation Framework?(There are three correct answers.)
Methodology
Content
Analytics
Tools
2. Where can we find additional information about SAP Activate? (There are three correct answers.)
Online Blogs
SAP Activate Community
SAP Learning Hub
SAP Cloud ALM
3. Select the major implementation roadmap types.(There are four correct answers.)
Cloud Specific Methodology
On-Premise Specific Methodology
Hybrid Methodology
Upgrade Methodology
General Methodology
4. Which of the following is an example of an accelerator available on the SAP Signavio Process Navigator? (There are two correct answers.)
Test Case
Business Process Master List
Process Diagram
Project Plan
5. Which of the following is not a phase of SAP Activate?(Choose the correct answer.)
Discover
Prepare
Explore
Realize
Deploy
Hypercare
6. Which of the following are SAP Activate Workstreams?(There are three correct answers.)
Solution Adoption
Project Management
Technical Landscape
Extensibility
Training
7. Name all core dimensions that apply to clean core. (There are three correct answers.)
Reporting
Process
Integration
Database
Operating System
Extensibility
8. Related to Data, which of the following statements is correct?(Choose the correct answer.)
Measures must be in place to ensure that data is completed, correct, and compliant with industry and legal regulations.
Data is not required to be compliant with regulations.
Unstructured, incomplete, and inconsistent data is decoupled from clean core dimensions.
9. Which of the following does intense custom extension lead to?(There are two correct answers.)
Increased upgrade effort.
Reduced upgrade costs.
Quicker upgrades.
Increased maintenance.
10. How are the clean core principles embedded in the Governance & Framework of the RISE with SAP Methodology? (Choose the correct answer.)
Clean core principles are anchored into the Activate Methodology through clean core quality gates.
Clean core principles are embedded in the Run Phase of Activate Methodology.
Clean core principles are embedded in the Phases prepare & deploy of Activate Methodology.
11. For which SAP Activate phase of a transformation SAP Signavio is relevant?
(Choose the correct answer.)
Discover, Prepare
Explore
Discover, Prepare, Explore
All phases
12. What process related information does SAP Process Insights, discovery edition, provides you?(There are three correct answers.)
Identification of typical blockers and process break points
Correction recommendations
Innovation recommendations
Number of modifications
Custom Code enhancements
13. What are the top three questions that organizations need to consider during their move to SAP S/4HANA?(There are three correct answers.)
How does an organization ensure that the transformation adds value?
How does an organization make the transformation as fast as possible?
How to reduce the involvement of end-users?
How does an organization ensure that change is manageable?
How to replace SAP GUI with SAP Fiori?
14. What are the dimensions to transform successfully? (There are four correct answers.)
Business Strategy
Clean Core
Processes
Solutions
People
No business downtime during transformation
15. For which type of transformations SAP Signavio is relevant? (Choose the correct answer.)
New Implementation
System Conversion
Both
16. For which solutions can SAP Cloud ALM for Implementation be used? (There are four correct answers.)
SAP S/4HANA Cloud, Public Edition
SAP S/4HANA Cloud, Private Edition
SAP SuccessFactors
SAP Ariba
17. What content is available in SAP Cloud ALM for Implementation?(There are three correct answers.)
SAP Pricing Information
SAP Best Practice Processes
SAP Activate Roadmaps
SAP Test Automation Test Cases
18. Which of the following tools are recommended for managing your implementation? (There are two correct answers.)
SAP Signavio
SAP Best Practice Explorer
SAP Cloud ALM
SAP Focused Run
19. Which of the following capabilities are offered in SAP Cloud ALM for Implementation? (There are three correct answers.)
Project Management
Process Mining
Test Execution
Documentation Management
20. Select the main upgrade scenarios for SAP S/4HANA. (There are three correct answers.)
Purely technical approach
Leverage innovations
Implementation of new SAP S/4HANA
Embed LoB Products
21. For cloud-to-cloud integration scenarios, Process Orchestration (PO) and APIs are the recommended options to be used. (Choose the correct answer.)
True
False
22. User Acceptance Test is used to validate and verify the system components against Solution Documentation. (Choose the correct answer.)
True
False
23. Which of the following is the definition of Regression Test? (Choose the correct answer.)
To validate that all software module dependencies are functionally correct and that data integrity is maintained between separate modules for the entire solution.
Confirm that new functionality does not cause defects in existing functionality.
Validate and verify the system components against Solution Documentation.
To check if the system can support day-to-day business/user scenarios and ensure the system is sufficient and correct for business usage.
24. Select the right statements for SAP S/4HANA On-Premise Implementations. (There are three correct answers.)
Apply back to standard where possible.
Redesign custom code
Replatform custom code
Keep existing code as is
25. What can be found in the SAP Solution Implementation Roadmaps? (There are three correct answers.)
Deliverables in each phase
Value maps
Detailed description of implementation tasks
Accelerators to be used in the Project Library
26. Select the right statements. (There are two correct answers.)
SAP Cloud ALM helps you to implement and operate intelligent cloud and hybrid business solutions.
You benefit from an out-of-the-box On-Premise solution, designed as the central entry point to manage your SAP landscape with content-driven guided implementation.
SAP Cloud ALM is included in your cloud subscription containing Enterprise Support, cloud edition and in SAP Enterprise Support.
27. What are the enablement areas relevant for all customer team members coming from the business? (There are three correct answers.)
Workstream enablement
Solution expertise
Technical expertise
Project management
28. Which of the following is the definition of Integration Test? (Choose the correct answer.)
To validate that all software module dependencies are functionally correct and that data integrity is maintained between separate modules for the entire solution.
Confirm that new functionality does not cause defects in existing functionality.
Validate and verify the system components against Solution Documentation.
To check if the system can support day-to-day business/user scenarios and ensure the system is sufficient and correct for business usage.
29. There are several SAP options for creating data insights and providing summaries in a structured format for SAP customers. Which of the following are part of the SAP Analytics and Reporting Portfolio? (There are four correct answers.)
SAP Analytics Cloud
SAP S/4HANA Embedded Analytics
SAP Process Orchestration
SAP Hybrid Solutions (BI/Planning/Predictive)
SAP Analytics Hub
30. What can you do with Guided Configuration? (There are four correct answers.)
Initial configuration of your solution and recording of updates for continuous innovation
Test your configured business processes
System conversion
Data migration
Evaluate activated business processes and country versions
31. What are the substreams in the data management workstream? (There are three correct answers.)
Data volume management
Data aging
Data migration
Master data management
32. A scope item is a business process. (Choose the correct answer.)
True
False
33. What milestones are part of the project experience in the central configuration system? (There are two correct answers.)
Scope
Design
Build
Configuration
34. S/4HANA Cloud includes traditional flexibility and full scope. (Choose the correct answer.)
True
False
35. Which system is used to configure SAP S/4HANA Cloud? (Choose the correct answer.)
Business Technology Platform (BTP)
Central Configuration System
SAP S/4HANA Starter System
IMG (Implementation Guide)
36. What are the primary steps of system conversion? (There are two correct answers.)
Database Migration
Data Migration
Software Update
Lift and Shift
37. What partner types does SAP deliver RISE with SAP services with? (There are two correct answers.)
Services Partner Community
Infrastructure Partners
Implementation Partners
Hyperscaler Partners
38. Side by Side extensibility enables loosely coupled development. (Choose the correct answer.)
True
False
39. Which of the following are part of SAP’s Security Strategy? (There are two correct answers.)
Comprehensive Contracts
Database encryption
Ethical Hacking
Independent Audits
40. Select the right statement. (Choose the correct answer.)
Selective Data Transition path works only with new implementation scenarios.
Selective Data Transition path works only with system conversion transition scenarios.
Selective Data Transition path works with both, new implementation and system conversion transition scenarios.
41. From which platform are you able to deploy preconfigured system templates? (Choose the correct answer.)
Business Technology Platform
Central Configuration System
SAP Cloud Appliance Library
SAP Data Center
42. Which of the following are covered by the SAP readiness checks? (There are two correct answers.)
Custom Code Development
Configuration
Data Volume Management
Master Data
43. The ‘Get Support‘ application helps to resolve a support issue in real time or reach SAP experts with relevant information through an AI-enabled framework. (Choose the correct answer.)
True
False
44. Which of the following adoption approaches are used in the ERP Implementation Strategies?(There are two correct answers.)
Big Bang adoption
Passthrough adoption
Phased adoption
Exhaustive adoption
45. What is your central point of contact for all SAP customers, whether Cloud or On-Premise? (Choose the correct answer.)
Expert Chat
Ask an Expert Peer
Customer Interaction Center
Schedule a Manager
46. Which of the following statement are the true regarding the SAP Activate Community? (Choose the correct answer.)
It provides information only on Cloud deployments.
It provides information only on premise deployments.
It provides information on both premise and Cloud deployments.
47. Scrum Board is a tool that helps teams make Sprint Backlog items visible. The board can take many physical and virtual forms but it performs the same function regardless of how it looks. (Choose the correct answer.)
True
False
47. A burn-down chart is used to mark day-by-day how much remains of the scheduled work. (Choose the correct answer.)
True
False
48. Which of the following activities are performed in the Explore phase of SAP Activate in SAP S/4HANA Implementation? (There are three correct answers.)
Defining organizational structure
Adjusting predelivered master data for workshops
Creating sample transactional data for workshops
Adjusting custom code objects
Writing Technical Design Documents
49. Which of the following statements about Scrum is correct? (Choose the correct answer.)
In Scrum, as best practices, we have three main roles, and three artifacts or three ceremonies.
In Scrum, the team is self-organized, define all task necessary for all project life cycle.
The three ceremonies are Sprint Planning, Daily Scrum, Sprint Review (Retrospective).
Scrum Master defines and prioritizes features and gathers requirements.
50. In the context of Scrum, which of the following statements are correct? (There are two correct answers.)
Product Backlog is a list of features prioritized by business value, the items come from diverse sources, including the Scrum team.
Sprint backlog is a subset of Product Backlog loaded onto the Sprint’s timebox. It's the list of work the team is addressing during the current Sprint.
Burndown Chart Provides visibility into the Product Backlog, illustrate progress by the team, work is in horizontal and time is in the vertical.
51. Which of the following are available in the initial SAP Activate Community Page? (There are four correct answers.)
Information on implementation roadmaps
Blogs on SAP Activate topics
Latest SAP Activate content updates
Resources for SAP Activate project deployments
52. Which of the following are the key responsibilities of the Scrum Master? (There are three correct answers.)
Responsible for the project delivery
Task initiator
Team protection
Leadership skill
Team support
53. Product Backlog is simply a list of all things that needs to be done within the project. It replaces the traditional requirements specification artifacts. (Choose the correct answer.)
True
False
54. The Product Owner's responsibilities can be grouped into three levels – strategic, tactical, and operational. (Choose the correct answer.)
True
False
55. The main purpose of the Explore phase is to perform a Fit-to-Standard Analysis to validate the solution functionality included in the project scope and to confirm that the business requirements can be satisfied. (Choose the correct answer.)
True
False
56. A definition of Ready signifies that a User Story has been completed. (Choose the correct answer.)
True
False
57. Which of the following dimensions need to be considered during prioritization? (There are three correct answers.)
Importance
Scaling
Integration
58. A User Story map arranges user stories into a useful model to help understand the functionality of the system, identify holes and omissions in your backlog, and effectively plan holistic releases that deliver value to users and business with each release. (There are three correct answers.)
True
False
59. Regarding user stories and releases, which of the following statements are correct? (There are three correct answers.)
A User Story is a tool used in Agile software development to capture a description of a software feature from an end-user perspective. The User Story describes the type of user, what they want, and why.
A User Story helps to create a simplified description of a requirement.
A release is a deployable software package that is the culmination of several iterations. Releases can be made before the end of an iteration.
60. Sprint Execution is the period during which the task-level work is performed by the development team to complete the features committed to during Sprint Planning. (Choose the correct answer.)
True
False
61. Each team has their own estimated velocity that should not be extrapolated or compared to the velocity of the other teams. (Choose the correct answer.)
True
False
62. In the System conversion to SAP S/4HANA Deploy phase, which of the following tasks are included? (Choose the correct answer.)
Final testing
Hyper care support
Scheduling project plan
Interface setup
63. In which of the following project phases is it important to plan and schedule data loads followed by load validation activities? (Choose the correct answer.)
Prepare
Realize
Explore
Deploy
64. The Value-Driven approach puts the focus on the Project success. (Choose the correct answer.)
True
False
65. Agile projects use iterative incremental build to focus team on finite number of priorities to address in each Sprint. (Choose the correct answer.)
True
False
66. The Solution Validation Workshops validate the baseline build from which we can identify delta requirements and gaps for the Backlog and create the agreed process documentation for the Explore phase. (Choose the correct answer.)
True
False